Who regulates manufactured homes in Virginia?
The local building official handles the permits, inspections and certificate of occupancy. The state oversees the manufactured housing program and licenses installers through a separate agency. Health, utilities and road access are each handled separately.
| What | Who handles it | What it does not cover |
|---|---|---|
| State manufactured housing program | DHCD, State Building Codes Office | The local application |
| Installer licences | DPOR Board for Contractors, manufactured housing (MHC) specialty | Local permits |
| Installation and site permits, inspections, certificate of occupancy | The local building official, with the zoning office | Other jurisdictions |
| Septic or well, utilities, road entrances | The Health Department, the utility providers, and VDOT where it applies | The building permit |
DHCD’s manufactured housing page describes the state program and the local responsibility for installation and site permits.
Is there one permit for a manufactured home in Virginia?
No. The local building permit, zoning, health department approval, a road entrance permit and any land disturbance approval are separate. A HUD label covers how the home was built in the factory. It does not replace any of these local approvals.
How do you find the right permit office for a property?
Start from the parcel, not the mailing address. A postal city does not tell you which office has jurisdiction.
- Collect the parcel number, legal description, survey or plat, street address and ownership details.
- Confirm whether the property is in a county, a town or an independent city, how it is zoned, and which office issues the permit.
- Identify the septic or sewer route, the water and electric providers, and whether a road entrance permit is needed.
- Note whether the home is new, used and being relocated, a replacement on the same site, or built before June 15, 1976. Requirements can differ for each.
Virginia’s independent cities are separate from the counties around them. Staunton and Waynesboro, for example, do not follow Augusta County’s rules.
What does Virginia require?
Local enforcement. Code of Virginia § 36-85.11 sets out local enforcement, along with site, utility and skirting requirements.
Installation to the manufacturer’s instructions, and a certificate. Under 13VAC5-95-60, the installer follows the manufacturer’s instructions. The installer then gives an installation certificate to the homeowner, and to the building official when asked, before the certificate of occupancy is issued.
A licensed installer. The DPOR Board for Contractors licenses installers under the manufactured housing (MHC) specialty. It covers installation, removal and certain internal tie-ins, but not necessarily every foundation or outside utility task, which can need other licensed trades. DHCD’s installer training guide notes that finishing the course is not, on its own, an installer licence.
The right home category. HUD-code manufactured homes, modular (industrialized) buildings and homes built before the HUD code are different categories with different requirements. Pick the manufactured home category on local forms.
What do Virginia counties ask for?
There is no statewide county checklist. Here is what three counties publish, as checked on November 17, 2026. Each office can ask for more, so confirm before you submit.
Culpeper County
Building Department, 302 N. Main Street, Culpeper. 540-727-3405.
Culpeper County’s digital submission checklist has separate sections for homes built before and on or after June 15, 1976. For a HUD-code home it asks for:
- the manufacturer’s installation instructions and options
- the exact unit and foundation details
- an installation summary
- tie-down documents
- related egress plans
The checklist separates town and county zoning. The county’s citizen portal has a residential manufactured home application category.
Caroline County
Planning and Community Development, 233 W. Broaddus Avenue, Bowling Green. 804-633-4303.
Caroline County’s permit packet covers single-wide and double-wide homes. It includes:
- a model setup and site sheet
- floor and site information
- health department approval
- land disturbance and road access forms, where they apply
- survey wording for smaller lots
- the applicant’s certification and contractor information
- an owner affidavit that is witnessed or notarized
The packet asks whether a replacement home stays in the same spot on the property. A certificate of occupancy is required before the home is used. Property in Bowling Green or Port Royal may involve the town as well.
Augusta County
Building Inspection.
Augusta County’s residential permit process has a manufactured home section covering:
- zoning
- health department approval; accepting an existing septic system is a separate step
- road entrance approval, including for existing driveways and replacement homes
- a sketch of the parcel
Inspections include the supports and setup and the marriage wall. The certificate of occupancy follows the final inspections and the health department’s approval to operate. Skirting is followed up separately. These are county rules; Staunton and Waynesboro are independent cities with their own.
What does a site plan need to show?
It depends on the office. Augusta County asks for a parcel sketch. Caroline County has a site sheet and asks for a survey on smaller lots. Before drawing, get the office’s own list.
Stampd draws site plans for manufactured home placements to the receiving office’s requirements.
What happens after the home is installed?
Several things happen separately:
- Inspections. Supports, setup and the marriage wall are inspected before they are covered up, as the county’s sequence requires.
- The installation certificate. The installer gives it to the homeowner, and to the building official when asked.
- Certificate of occupancy. Issued by the local building official after the finals and any health department approval. Ask the utility separately what it needs to connect power.