Who regulates manufactured homes in Tennessee?
The state licenses installers and runs the installation decal program. The county or city can require its own placement permit. Septic, moving and utilities are each handled separately.
| What | Who handles it | What it does not cover |
|---|---|---|
| Installer licences, installation permits and decals, reporting | State Fire Marshal’s Office, Manufactured Housing section (Department of Commerce and Insurance) | Local placement approval |
| Selling the installation decal | The county clerk | Zoning or placement |
| Placement permits, zoning and trade permits | The county or city codes or planning office | Other jurisdictions |
| Septic or sewer | TDEC or the sewer provider | Placement approval |
| Moving the home on the road | TDOT and the local road officials | Approval at the new site |
The installation program is separate from the state’s residential building permit program. The residential program’s FAQ excludes manufactured homes and has a separate site work permit category. That does not mean no permits: local placement permits still apply where a county or city requires them.
Is there one permit for a manufactured home in Tennessee?
No. The state installation decal and the local placement permit are different things, and finishing one does not finish the others. Depending on the property, septic approval, trade permits, a moving permit and utility release also apply.
How do you find the right permit office for a property?
Start from the parcel, not the mailing address. A postal city does not tell you which office has jurisdiction.
- Collect the parcel number, legal description, survey or plat, street address and ownership details.
- Confirm whether the property is inside a city, how it is zoned, and whether that office requires a placement permit.
- Identify the sewer provider or septic authority, the water and electric providers, and road access.
- Note whether the home is new, used, a replacement or going into a park. Requirements can differ for each.
What does Tennessee require?
A licensed installer. The State Fire Marshal’s installer FAQ requires an approved, active installer licence before installation.
An installation permit (decal), bought from the county clerk. The Shelby County Clerk, for example, lists the decal at $45. That is the decal only, not the cost of the project.
The decal steps, in order.
| Step | What the State Fire Marshal says |
|---|---|
| Buy the decal | Before installation, once the home is on site or ready. Not in bulk (March 2024 guidance) |
| Place the decal | After setup is complete |
| Report the installation | Within seven calendar days |
Current rules only. Parts of the older installation rules were repealed with effect from December 22, 2024, according to the state’s rule history. Older copies of the rules that still turn up in searches are out of date.
A moving permit. Moving a home on the road can need an oversize permit and route from TDOT, plus any local road permissions.
What do Tennessee counties and cities ask for?
There is no statewide local checklist. Here is what two counties and one city publish, as checked on November 17, 2026. Each office can ask for more, so confirm before you submit.
Rutherford County
Building Codes, 1 South Public Square, Room 101, Murfreesboro. 615-898-7734.
Rutherford County says a local permit is required to place a manufactured home. It lists owner permission forms among its building forms. Its FAQ and its linked application describe different ways to submit, in person and by email, so ask which applies to a manufactured home. These are county rules; property inside Murfreesboro or another city follows city rules. The county also publishes monthly permit reports by permit type.
Hamblen County
Planning and Zoning, 511 West Second North Street, Morristown. 423-581-1373.
Hamblen County’s placement packet asks for:
- the placement application
- septic approval
- a site plan showing setbacks and the driveway
The office supplies the address and access paperwork, and stormwater materials where they apply. The packet includes an inspection checklist. Property inside Morristown follows city rules.
Johnson City
Development Services, 601 East Main Street. 423-434-6047.
Johnson City’s permit information, revised February 2022, covers installation and replacement permits. It asks for:
- the application and a site plan
- the licensed installer’s contact details
- utility taps
- separate permits for trade work and accessory structures
Building, trade and site finals and a certificate of occupancy come before the home is occupied. Replacing a home in a nonconforming park has its own rules, separate from individual lots. These are city rules, not county rules for Washington, Carter or Sullivan counties.
What does a site plan need to show?
It depends on the office. Hamblen County wants setbacks and the driveway shown. Johnson City asks for a site plan with the application. Before drawing, get the office’s own list.
Stampd draws site plans for manufactured home placements to the receiving office’s requirements.
What happens after the home is installed?
Several things happen separately:
- The state decal and report. The decal is placed after setup is complete, and the installation is reported within seven calendar days.
- Local inspections. Trade, site and placement inspections, as the county or city requires. Johnson City issues a certificate of occupancy before the home is occupied.
- Power. The decal alone does not release power. Ask the local office and the utility what they need.