Who issues the permit in Madison County?
| What | Who | Contact |
|---|---|---|
| 911 address, electric service permit, floodplain permit | Madison County Rural Development | 101 West Main, Suite B-13, Madisonville, TX 77864. 936-348-3810 |
| Driveway on a county road | The county commissioner for the precinct | 936-241-6200 (precinct extensions on the form) |
| Septic | Madison County septic inspector | 936-241-6200, ext. 1220 |
Step 1: the 911 address
Submit the Physical Address Request/Verification form. It lists manufactured homes and requires a drawing of the site showing current and future structures and driveways. Allow 7 to 10 working days.
Step 2: the driveway permit
A driveway onto a county road needs a permit from the precinct commissioner (policy enacted January 24, 2022). The form lists a single manufactured home or RV and manufactured home or RV parks.
- No fee.
- No work may start until the permit is issued.
- Include a survey or site map showing the proposed work.
- The culvert must be at least 24 feet long and 15 inches in diameter, installed as the county approves.
- Give a copy of the completed form to Rural Development when requesting a new 911 address.
- On a state highway, get a TxDOT permit instead.
Step 3: the electric service permit
Before power is connected (temporary pole or permanent), Madison County requires an electric service permit:
- $30, cash, check or money order to Madison County
- the septic inspector’s signature confirming the septic requirement, before the form is submitted
- Rural Development reviews the floodplain and verifies the 911 address
- valid for one year; applications can be closed if development guidelines are not met within six months
Is a floodplain permit needed?
In a flood zone, yes. The application asks for:
- a site plan drawn to scale showing all existing structures, water bodies, adjacent roads, lot dimensions and the proposed development
- development plans to scale, including anchoring details and the proposed lowest floor elevation
- an emergency plan for the construction phase
No work may start until the permit is issued. It expires if work does not start within six months, and the home cannot be occupied until a Certificate of Compliance is issued after the as-built elevations are submitted.
What does the state require in Madison County?
The same as everywhere in Texas: a TDHCA-licensed installer, installation to the right instructions, and a Notice of Installation (Form T) filed with TDHCA after the home is installed. Form T is a report to the state, not a local permit. The Texas guide explains each step.
What should the site plan show?
Madison County asks for drawings at three points: the 911 request (structures and driveways), the driveway permit (the proposed work) and, in a flood zone, a scaled site plan with structures, water, roads and lot dimensions. One site plan covering the home, the driveway and culvert, the septic system, the property lines and any flood zone serves all three. Stampd draws site plans for manufactured home placements.
More help with Texas placements
The Texas manufactured home permit guide covers the state rules that apply in every county. Stampd draws site plans for manufactured home placements to the receiving office's checklist, and handles permit submission and follow-up for dealers and installers.