Who issues the permit in Frio County?
The Frio County Road & Bridge Department reviews septic permits, subdivision plats and right-of-way utility permits, and assists with 911 addresses.
Road & Bridge Department, 2207 BI 35 E, Pearsall, TX 78061. 830-505-7402.
Why is a flood study needed?
The county’s septic guidelines say FEMA maps are not available for unincorporated Frio County, so a professional engineer must prepare a flood study. The Frio County Flood Damage Prevention Ordinance of May 23, 2016 requires a floodplain development permit for all development, and the application is filed with the septic application.
What does the septic application need?
- A system designed by a professional engineer or registered sanitarian. All systems must be designed.
- A flood study by a professional engineer.
- The Frio County Floodplain Development Permit application.
- Proof of legal description: a deed, plat, survey or similar.
- A set of plans (see below).
- A site evaluation by a licensed site evaluator.
- The licensed installer’s signed confirmation of site inspection.
Return everything to the Road & Bridge office. Only original designs are accepted; no copies, faxes or emails.
| Permit | Fee |
|---|---|
| Residential system | $200 |
| Commercial or aerobic system | $450 |
Pay by money order or cashier’s check.
How do I get a 911 address?
Request it from Frio County 9-1-1 Addressing, online or by phone. GPS coordinates taken at the property entrance are required, no exceptions. On a TxDOT highway, the TxDOT driveway permit comes first.
What does the state require in Frio County?
The same as everywhere in Texas: a TDHCA-licensed installer, installation to the right instructions, and a Notice of Installation (Form T) filed with TDHCA after the home is installed. Form T is a report to the state, not a local permit. The Texas guide explains each step.
What should the site plan show?
Frio County’s septic plans must show the property lines, the proposed septic system and every improvement: any water well, the home, utility lines, outbuildings and easements. They must also mark the 100-year floodplain boundaries, or state that there is no floodplain on the tract. Stampd draws site plans for manufactured home placements.