Who issues the permit in Dallas County?
Most of Dallas County is inside a city, and each city runs its own permits. Check the parcel first.
For the unincorporated areas, the Dallas County Department of Unincorporated Area Services (DUAS) issues the permits.
DUAS, Records Building, 500 Elm Street, Suite 6100, Dallas, TX 75202. 214-653-6565.
Dallas County says development activities in the unincorporated areas need a permit, including residential construction or installation, grading or filling, floodplain development and septic (OSSF) systems. All permits are applied for online through MyGovernmentOnline.
What are the fees?
From the DUAS fee schedule, updated August 30, 2023:
| Permit | Fee |
|---|---|
| Manufactured home or RV placement | $50 |
| Driveway or culvert | $75 |
| Development permit, Level 1 | $35 |
| Development permit, Levels 2 and 3 | $100 |
| Development permit, Level 4 | $250 |
| Residential building permit | $100 |
| Notice of residential construction | $50 |
| Right-of-way or utility | $75 |
| Pre-development meeting | $35 |
Septic fees follow the county Health and Human Services environmental health fee schedule. County Clerk filing fees are extra where a document must be recorded.
How long does an application stay open?
The application file stays open for one year from the date Dallas County receives it. The owner must complete and submit all documents within that time. No development activity is authorized until the permits are approved and issued.
What does the state require in Dallas County?
The same as everywhere in Texas: a TDHCA-licensed installer, installation to the right instructions, and a Notice of Installation (Form T) filed with TDHCA after the home is installed. Form T is a report to the state, not a local permit. The Texas guide explains each step.
What should the site plan show?
In unincorporated Dallas County, the placement, driveway, floodplain and septic permits all depend on where the home, the driveway, the septic system and any flood zone sit on the lot. Show them with the property lines and distances. Stampd draws site plans for manufactured home placements.
More help with Texas placements
The Texas manufactured home permit guide covers the state rules that apply in every county. Stampd draws site plans for manufactured home placements to the receiving office's checklist, and handles permit submission and follow-up for dealers and installers.