Who issues the permit in Colorado County?
The Colorado County Permit Office at 305 Radio Lane, Columbus, TX 78934 handles both parts.
| Desk | Handles | Phone |
|---|---|---|
| Floodplain Management and 911 Rural Addressing | Development permits, 911 addresses, flood zone review | 979-732-6380 |
| On-Site Sewage Facility (OSSF) | Septic permits and inspections | 979-732-2435 |
Step 1: the development permit and 911 address
No construction can begin without a development permit, and the application lists manufactured homes. The owner must fill out and sign it.
| Item | Fee |
|---|---|
| Residential development permit | $30 |
| 911 address sign | $10, plus $10 if mailed |
| Commercial development permit | $350 |
Bring proof of ownership: the first page of the deed or a current property tax receipt. You may be asked to mark the planned entrance and where the home will sit.
Once approved, the county sends a letter with the 911 address and issues a green permit plaque that must be visible from the road during construction. The permit is good for one year to start construction.
What about the flood zone?
The Floodplain Manager checks each application for the flood zone (X, 0.2%, A or AE) and whether the home sits in a flood hazard area. If it does, an elevation certificate may be required, and the county’s Flood Damage Prevention Ordinance applies.
Step 2: the septic permit
A septic permit is required for every septic installation or repair.
- The landowner applies and pays: $250 residential, $350 commercial.
- A licensed site evaluator, registered sanitarian or engineer does a soil survey and site evaluation.
- If the site needs something other than a standard gravity system, an engineer or registered sanitarian designs it.
- The evaluation, soil survey and design go to the Permit Office for approval.
- The installer gets a Permit to Construct and builds the system.
- The installer books the final inspection. The system cannot be covered before it.
Surface irrigation and spray aerobic systems need a two-year maintenance contract. Permits are valid for one year.
What does the state require in Colorado County?
The same as everywhere in Texas: a TDHCA-licensed installer, installation to the right instructions, and a Notice of Installation (Form T) filed with TDHCA after the home is installed. Form T is a report to the state, not a local permit. The Texas guide explains each step.
What should the site plan show?
The 911 address, flood zone check and septic design all depend on where the entrance, the home and the system sit. Show the home, the driveway entrance, the septic system and its field, any well, the property lines and any flood zone. Stampd draws site plans for manufactured home placements.