Who issues the permit in Collin County?
For property outside city limits, Collin County Development Services issues the permits, through the county’s Citizen Self-Service Portal. The county says any residential project that disturbs ground or adds footprint on a parcel needs a permit.
| Where the property is | Who permits |
|---|---|
| Unincorporated Collin County | Collin County |
| A city’s ETJ | Collin County, with an ETJ Verification form signed by the city |
| Inside a city | That city. For septic, check TCEQ’s list of authorized agents; if the city is not listed, Collin County is the agent |
There is no county zoning outside city limits, apart from sexually oriented businesses, salvage and junk yards, and animal slaughter operations. Use the county’s interactive map to check whether a parcel is in a city, an ETJ or the floodplain. The Fire Marshal’s Office is the cashier for all permits. Culverts, driveways and right-of-way go through Public Works.
How do the development and septic permits fit together?
- If the home connects to a new septic system, apply for the development permit first. County staff then send the associated septic (OSSF) permit through your portal.
- Do not apply for a separate development permit and septic permit.
- Adding a structure on a property with an existing septic system needs a review of the existing system.
- Collin County applies the state Chapter 285 rules plus its own stricter court order.
- Systems that require maintenance need an affidavit filed with the County Clerk (2300 Bloomdale Rd., Suite 2104, McKinney).
- A septic permit expires after 365 days of no activity.
What is the minimum lot size for septic?
| When the lot was divided | Minimum |
|---|---|
| Before 1983 | Existing small lots may be allowed with proof the lot existed then and a compliant design |
| 1983 to 2008 | 1 acre, or 1.5 acres with a water well |
| 2008 or later | 1 usable acre, or 1.5 acres with 1 usable acre if there is a water well |
“Usable” means usable for the septic components and disposal area, excluding most easements and ponds. A lot made smaller than required after these dates is ineligible for septic, except where land was taken by a government for a road.
Addressing and power
- Collin County does not address raw land. The address is assigned during permitting. Mark the home’s location correctly on the site map or addressing is delayed.
- Meter releases are requested electronically with the permit number and full address.
- Permanent power needs a passing third-party electrical inspection, and the septic system must have passed both its initial and final inspections.
- Releases are approved or denied within three business days.
What does the state require in Collin County?
The same as everywhere in Texas: a TDHCA-licensed installer, installation to the right instructions, and a Notice of Installation (Form T) filed with TDHCA after the home is installed. Form T is a report to the state, not a local permit. The Texas guide explains each step.
What should the site plan show?
Collin County assigns the address from the location marked on the site map, and the septic review depends on the usable acreage once easements and ponds are excluded. Show the home, the septic system and disposal area, any well, easements, ponds, the driveway and the property lines, with distances. Stampd draws site plans for manufactured home placements.