Caldwell County, Texas

Manufactured home permits in Caldwell County, Texas

Sources last checked

Under the Caldwell County Development Ordinance, installing a manufactured home in unincorporated Caldwell County needs a Residential Construction Permit. The application needs the plat or metes and bounds with a survey sketch, the deed, tax certificates, a sketch of the site, proof of water, and the approved septic permit. Within 300 feet of a floodplain, the floor must be at least 2 feet above base flood elevation.

manufactured homes installed in Caldwell County in 2025 (TDHCA installation records)
163
above base flood elevation for the floor of a home inside or within 300 feet of a floodplain
2 ft
the minimum the ordinance says a home's foundation should sit above the surrounding ground
12 in
Get a quote for Caldwell County For dealers and installers

Who issues the permit in Caldwell County?

For property outside city limits, Caldwell County issues a Residential Construction Permit under its Development Ordinance. The ordinance defines a residential structure as including a manufactured home, and requires the permit for:

  • construction or installation of a residential structure
  • additions that add bathrooms or bedrooms
  • rebuilding after fire or flood where the cost exceeds 30% of the pre-damage value

In a city’s extraterritorial jurisdiction, an interlocal agreement may apply; without one, both the city and the county must approve, and the stricter rule wins. A property inside Lockhart, Luling or another city follows that city’s rules.

What does the application need?

Item What the ordinance asks for
Lot record The recorded plat for a platted lot, or the metes and bounds description and surveyor’s sketch for an acreage tract
Ownership A copy of the deed or other recorded ownership document
Taxes Certificates showing all current taxes (county, city, school) are paid
Site sketch See below
Water A paid meter or impact fee receipt, a water bill, a well driller’s log, or an engineered or certified rainwater system
Septic A copy of the approved septic permit issued through Caldwell County, where the home uses one
Floodplain Base flood elevation (with elevation certificate), lowest existing floor and proposed elevation, where the home is in or within 300 ft of a floodplain

The permit is valid for two years or until construction is complete, whichever comes first.

What must the site sketch show?

The ordinance lists it:

  • existing structures
  • existing and proposed driveways
  • approximate distances from the home to the property boundaries
  • the floodplain
  • easements
  • residential or public water wells
  • the septic system, including tanks, pumps and effluent fields

Elevation and foundation rules

  • The foundation of a residential home should be at least 12 inches above the surrounding ground.
  • Inside or within 300 feet of a floodplain, the first finished floor must be at least 2 feet above the adjoining base flood elevation, documented by an elevation certificate and an engineer’s or surveyor’s floor elevations.

Does the lot qualify?

The parcel must be one of:

  • an original tract, existing in its current configuration before September 1, 1997
  • a lot legally platted through the Caldwell County Commissioners Court
  • exempt from platting under the ordinance or state law

Exempt tracts still need 50 feet of frontage on a state road, county road or private street, and must follow the county’s driveway, septic, floodplain and 911 addressing rules. Any work in the county right-of-way, including a driveway apron, needs a right-of-way permit.

What does the state require in Caldwell County?

The same as everywhere in Texas: a TDHCA-licensed installer, installation to the right instructions, and a Notice of Installation (Form T) filed with TDHCA after the home is installed. Form T is a report to the state, not a local permit. The Texas guide explains each step.

What should the site plan show?

Caldwell County’s sketch list is detailed: structures, driveways, distances to every boundary, floodplain, easements, wells and the full septic layout. A measured site plan covering all of it, with floor elevations near a floodplain, matches the ordinance item for item. Stampd draws site plans for manufactured home placements.

More help with Texas placements

The Texas manufactured home permit guide covers the state rules that apply in every county. Stampd draws site plans for manufactured home placements to the receiving office's checklist, and handles permit submission and follow-up for dealers and installers.

FAQ

Common questions

Does a manufactured home need a permit in Caldwell County, Texas?

Yes. The Caldwell County Development Ordinance requires a Residential Construction Permit for the construction or installation of a residential structure, and it defines a residential structure as including a manufactured home. The permit is valid for two years or until construction is complete, whichever comes first.

What does a Caldwell County Residential Construction Permit application need?

The recorded plat for a platted lot, or the metes and bounds description and surveyor's sketch for an acreage tract; the deed; tax certificates showing current taxes are paid; a sketch of the proposed construction; proof of potable water (a paid meter receipt, water bill, well driller's log or a certified rainwater system); and, with a septic system, a copy of the approved septic permit issued through Caldwell County.

What must the Caldwell County site sketch show?

The location of existing structures, existing and proposed driveways, approximate distances from the home to the property boundaries, the floodplain, easements, residential or public water wells, and the septic system including tanks, pumps and effluent fields.

What are the floodplain rules for a home in Caldwell County?

If the home is inside or within 300 feet of a floodplain, its first finished floor must be at least 2 feet above the adjoining base flood elevation. The application then needs the base flood elevation (an elevation certificate is required), the elevation of the lowest existing floor determined by a professional engineer or surveyor, and the proposed elevation.

Does the lot itself have to qualify in Caldwell County?

Yes. The ordinance says the parcel must be an original tract (existing in its current configuration before September 1, 1997), a lot legally platted through the Commissioners Court, or exempt from platting. Even exempt tracts need 50 feet of frontage on a state road, county road or private street.

Get a quote

Tell us about a project, or about the work you have coming up.

Whether you have one home to place or a regular flow of installs, we will talk through what you need. Pricing is agreed in a proposal, based on the services you choose and your project volume.

Prefer to talk first? Call 936-444-4077 or email info@stampdpermits.com.

Service needed

Rather talk? 936-444-4077

Buying a home?

Stampd works with manufactured home dealers and installers, not directly with homeowners. Ask your dealer or installer whether they use Stampd.

Sources

Every fact on this page comes from one of these, checked on November 23, 2026. Rules and fees change; confirm with the office before you submit. This page is general information, not legal advice.

  1. Caldwell County Development Ordinance (amended February 14, 2023), Section 4.4 Residential Construction Permit
  2. TDHCA, Manufactured Housing installation records Installations reported in Caldwell County, January to December 2025