Who issues the permit in Burleson County?
For property outside city limits, three county offices, all in Suite 303 of the Burleson County Courthouse, 100 W. Buck St., Caldwell, TX 77836:
| Office | What it handles | Phone |
|---|---|---|
| Environmental Department | Septic (OSSF) permits | 979-567-2360 |
| 911 Addressing | Physical addresses and address verification letters | 979-567-2007 |
| Floodplain office | Floodplain permits for development in the floodplain | 979-567-2333 (county main line) |
Inside the cities of Caldwell, Somerville and Snook, call the city for floodplain information.
Step 1: get the 911 address
Burleson County addresses by driveway and structure, and each structure connected to a septic system needs its own physical address. The 911 Addressing office must issue or verify the address before the septic application, and its address verification letter goes in with it.
Address requests can be made online, by email, in person or by post. They usually take less than a day, and up to five business days. If a road has to be mapped, allow up to four weeks. You will need the appraisal district property ID (R number).
Step 2: the septic (OSSF) permit
Every septic system in Burleson County needs a permit, regardless of acreage. The county adopted stricter rules than the state, so the ten-acre exemption does not apply. Homeowners may not install their own system; a licensed installer must.
| Fee | Amount |
|---|---|
| Residential | $330 |
| Commercial | $540 |
Pay by check or money order to Burleson County. Submit everything together, in person:
- the Application for an On-Site Sewage Facility (original)
- a copy of the 911 address verification letter
- the OSSF technical sheet, completed by the installer (original)
- the site and soil evaluation
- the system design
- a recorded Affidavit to the Public (two pages) and a signed maintenance contract, if the system type requires them
- a Property Owner Release, if someone other than the owner is applying
Documents must be originals or scanned copies. Screenshots and photos are refused, and applications cannot be emailed. The application asks for the type of structure (for example a manufactured home), its living area, the year built, the number of bedrooms and the water source, and an active water connection is required.
The county must approve or deny the plans within 30 days. The Authorization to Construct goes to the installer and is valid for one year. After the construction inspection passes, the county issues a License to Operate, which is required before the system is used.
Connecting to an existing system needs a transfer of ownership application and floor plans, so the county can confirm the system is permitted and sized for the home. A new home can share an existing system only if the original design included both structures.
Two or more homes on one tract
| Situation | What Burleson County requires |
|---|---|
| One home or RV on one tract | No affidavit |
| Two or more, not rented | Affidavit of Non-Rental, filed with the County Clerk, copy with the septic application. It transfers to future owners |
| Two or more, rented | Burleson County subdivision approval before any septic application |
Is a floodplain permit needed?
Only for development inside the floodplain. There, the application, plans and specifications must be approved before construction begins. You need the legal description from the deed. Check the parcel on the FEMA flood map first.
What does the state require in Burleson County?
The same as everywhere in Texas: a TDHCA-licensed installer, installation to the right instructions, and a Notice of Installation (Form T) filed with TDHCA after the home is installed. Form T is a report to the state, not a local permit. The Texas guide explains each step.
What should the site plan show?
The septic design and any floodplain review depend on where the home, the system and its field, any well, each driveway and the property lines sit. Show them with distances, along with any part of the lot in the floodplain. Stampd draws site plans for manufactured home placements.