Who issues the permit in Bastrop County?
For land outside city limits, Bastrop County Development Services issues a development permit.
Development Services, 211 Jackson Street, Bastrop, TX 78602. 512-581-7176.
Bastrop County does not issue building permits or certificates of occupancy. That does not mean no permit: external development needs a development permit, and the septic (OSSF) permit is part of the same submission where there is no public sewer.
The cities of Bastrop, Elgin and Smithville have their own zoning. A property inside one of them follows that city’s rules, not the county’s.
What does every application need?
| Item | What Bastrop County asks for |
|---|---|
| Proof of ownership | Always |
| Site plan | Dimensioned, showing the proposed improvements and the existing buildings or structures |
| Survey or plat | A copy, always |
| Septic (OSSF) application | Filed at the same time as the development application where public wastewater is not available, with floor plans |
| Owner’s agent certificate | When someone other than the owner applies |
| More | The county may ask for more information as needed |
Applications and supporting documents are uploaded through MyGovernmentOnline, where you can also message Development Services staff. The county recommends contacting the office before submitting, because requirements can change without notice.
The county’s forms page also lists a work in right-of-way application, a temporary driveway application, residential driveway requirements, an address sign order form, and affidavits for aerobic septic systems and for a septic system on multiple lots.
How long do Bastrop County permits last?
| Permit | Expiry | Extension |
|---|---|---|
| Development permit | Valid when issued; expires if construction is not completed within three years | One-time 180-day extension, requested 30 days before expiry. The same extension applies to driveway permits |
| Septic (OSSF) permit | One year after the Authorization to Construct, or one year after the first site inspection if no Authorization was issued | None |
What other rules apply?
- Non-compliant property. Permits are not issued for non-compliant property unless there is a health or public safety reason, such as a failed septic system, approved by the department head.
- Bedroom additions. An addition with bedrooms needs septic review. If a revised septic design is needed, the development permit waits for the revised OSSF application.
- Pine Forest subdivisions. Single-family development there also needs pre- and post-development drainage maps signed and sealed by a registered professional engineer.
- Floodplain. Bastrop County has a Flood Damage Prevention Order and publishes guidance for shaded Zone X. Check the parcel on the county’s Development Services map viewer before ordering a site plan.
- Deed restrictions. The county does not place or interpret deed or property restrictions; that is for the owner to research.
What does the state require in Bastrop County?
The same as everywhere in Texas: a TDHCA-licensed installer, installation to the right instructions, and a Notice of Installation (Form T) filed with TDHCA after the home is installed. Form T is a report to the state, not a local permit. The Texas guide explains each step.
What should the site plan show?
Bastrop County asks for a dimensioned site plan with the proposed home and every existing building or structure, filed with the survey or plat. Where there is a septic system, the OSSF review also depends on where the home, the system and the property lines sit, so show them with distances. Stampd draws site plans for manufactured home placements to the county’s checklist.