Who issues the permit in Austin County?
Austin County Planning & Development, One East Main St., Bellville, TX 77418. 979-865-5911, ext. 5110 or 5111. Open 8:00 am to 5:00 pm.
This is Austin County, west of Houston, with Bellville as its county seat. It is not the City of Austin, which is in Travis County.
Get the permit before the home arrives. Austin County’s guidelines say a development permit must be obtained before anything is moved onto or built on the property, including placing a manufactured home, and a penalty may be charged. The 911 address and the permits must be posted on site for the final inspection.
Step 1: the 911 address
Get the 911 address from the Austin County Emergency Communication District, 842 W. Main, Bellville (979-865-1911). Keep the letter it issues; it goes in with the development application.
Step 2: the development permit
Attach to the development application:
- a recorded copy of the property deed
- the Emergency Communication District’s 911 address letter
- in a flood hazard area, an elevation certificate from a certified surveyor, needed before the permit is issued
What are the fees?
From the Permitting & Engineering Fee Schedule adopted December 22, 2025:
| Permit | Flood zone | Outside the flood zone |
|---|---|---|
| Residential (home and garage) | $200 plus 5 cents per sq ft of enclosed area | $100 |
| Culvert (owner supplies pipe; county does not install) | $200 plus $50 inspection | $200 plus $50 inspection |
| Septic, conventional system, one single-family home | $275 | $275 |
| Septic, aerobic, one single-family home | $375 | $375 |
| 911 address sign | $20 each | $20 each |
| Re-inspection, single-family residential | $100 | $100 |
Working without a permit costs the permit amount plus a penalty of twice that amount, or $25 a day, whichever is greater. Each day is a separate violation. Permit fees are non-refundable.
Step 3: the septic (OSSF) permit
Austin County issues the septic permit only after the development permit or an exemption certificate. The county suggests submitting the paperwork three to four weeks before installation. The application must be in the property owner’s name, not a company’s, and signed by the owner, not an agent. Attach:
- the site evaluation
- the design, for an alternative system
- a maintenance agreement, for aerobic systems
- a notarized Affidavit to the Public, with the original filed at the County Clerk’s office
- a recorded copy of the deed
Step 4: the culvert or driveway
- Stake the middle of the driveway with your name and 911 address.
- Fill in the culvert and driveway form.
- Meet the precinct commissioner or designee. The form must be signed by both the owner and the commissioner.
- Take the form to Planning & Development.
Culverts must be at least 30 feet wide. On a state highway or farm-to-market road, contact TxDOT at 979-865-3101 instead.
What does the state require in Austin County?
The same as everywhere in Texas: a TDHCA-licensed installer, installation to the right instructions, and a Notice of Installation (Form T) filed with TDHCA after the home is installed. Form T is a report to the state, not a local permit. The Texas guide explains each step.
What should the site plan show?
The development permit fee depends on the flood zone, and the septic design and culvert depend on where the home and driveway sit. Show the home, the septic system and its field, any well, the driveway and culvert, the property lines and any part of the lot in a flood hazard area. Stampd draws site plans for manufactured home placements.
More help with Texas placements
The Texas manufactured home permit guide covers the state rules that apply in every county. Stampd draws site plans for manufactured home placements to the receiving office's checklist, and handles permit submission and follow-up for dealers and installers.